NHPC has announced a board meeting on 30th June 2025 to approve the financial results for the quarter and half-year.
FY25 revenue rose 7% YoY to Rs. 8,994 Cr, but PAT fell 17% to Rs. 3,084 Cr due to lower generation from the Teesta-V outage and pay provisions. Q4 PAT jumped 29% to Rs. 894 Cr on a 25% revenue rise. The Parbati-II (800 MW) project is fully commissioned; Subansiri Lower (2,000 MW) is 96% complete, targeting May ’26 for full commissioning. Solar capacity expansion continues with 107 MW commissioned and 200 MW under EPC in Gujarat. Management expects generation recovery post-Teesta restoration and remains confident on project timelines and renewable diversification despite headwinds.