Alpha Tribe

Yash Highvoltage LtdImportant, 26-05-2026: Company Update

26-05-2026 · 12:27 pm

Yash Highvoltage Limited completed a "Vastu Pujan" at its new manufacturing facility in Vadodara, signaling key progress on the expansion project. Funded by IPO proceeds, this plant will produce Resin Impregnated Paper (RIP) / Resin Impregnated Synthetic (RIS) transformer condenser graded bushings. Office building construction is complete, and major plant and machinery are currently being installed and commissioned. Peripheral infrastructure development is in its final stages. The company anticipates commissioning to conclude by the end of Q1 FY26-27, with trial production expected to commence in Q2 FY26-27, enhancing capacity and utilizing IPO funds effectively.

No comments yet. Be the first to comment!

All announcements from Yash Highvoltage Ltd